Supplier Lead Time Log: First Receipt, Full Receipt and Availability
A supplier lead time log records when a purchase order was sent and when the related materials were received. It makes the start event, receipt event and source evidence visible so planners can distinguish an observed delivery duration from a promised date or an estimate.
APQC’s supplier lead time measure for purchased materials starts with transmission of the purchase order and ends when the business receives delivery, measured in days. The worksheet below is an original practical aid for recording those events, not a reproduction of an APQC form or a benchmark for your suppliers.
Decide which receipt event your team is measuring
A first partial receipt, a complete physical receipt and stock becoming available for use can happen at different times. Keep the events separate. If the planning question is when the whole required quantity became usable, label that duration explicitly instead of calling it the same measure as first receipt.
Before calculating, agree whether records describe an order, an order line or a scheduled delivery. Also state whether elapsed time uses calendar days or a defined working calendar, which time zone applies, and how partial quantities are handled. Compare records only when those conventions match.
An original supplier lead time worksheet
| Field | What to record | Suggested evidence |
|---|---|---|
| Record scope | Order and line identifiers, item, quantity, unit of measure and receiving location. | Approved purchase order and delivery schedule. |
| Start event | When the order was transmitted to the supplier. | Transmission record; keep approval and acknowledgement times separately. |
| Promise | Original promised receipt date and any agreed revision. | Supplier confirmation and dated change history. |
| Receipts | Actual receipt time and quantity for each partial delivery. | Receiving evidence linked to the order or line. |
| Availability | When material became available for the intended use, where relevant. | Release or availability record under the organisation’s process. |
| Data quality | Missing timestamps, corrections and when the event was entered into the system. | Source document or event log and correction note. |
| Follow-up | Unresolved question, named owner and review point. | Action log linked to the source record. |
Choose fields that match the decision. Retain the original promise alongside revisions so the team can understand what changed. Record the physical event time separately from a later data-entry time; a late system entry does not establish that the delivery itself was late.
Hypothetical example: one order, three useful end events
Hypothetical example, not HPA client data or a supplier benchmark: a buyer transmits an order for 100 identical units on day 0 at 09:00. All events below use the same time zone and elapsed calendar days. There are no cancellations or quantity changes in this example.
| Event | Elapsed day at 09:00 | Quantity or meaning |
|---|---|---|
| Order transmitted | 0 | 100 units ordered. |
| First physical receipt | 6 | 60 units received. |
| Remaining physical receipt | 8 | 40 units received; 100 in total. |
| All units available for use | 9 | The example’s internal release process is complete. |
Under these stated conventions, elapsed time to first receipt is 6 days; elapsed time to complete physical receipt is 8 days; elapsed time to full availability is 9 days. The difference between the last two events is an internal stage in this example. It should not automatically be assigned to the supplier as a delivery delay.
These observations describe one fictional order. They do not establish a reliable planning lead time, a normal range, a safety-stock requirement or a promised future delivery date.
What to check before using the log in planning
- Reconcile each receipt quantity and unit of measure with the relevant order or line.
- Keep open orders visibly pending. An order with no receipt date does not have a completed zero-day lead time.
- Separate missing evidence from a confirmed non-delivery, and give the investigation an owner.
- Review differences in items, locations, transport arrangements and order conditions before combining observations.
- Retain the individual records and explain exclusions before relying on a summary.
A historical log can support a planning discussion, but selecting a replenishment policy also requires demand information, uncertainty, service requirements and relevant constraints. Do not change a stock parameter solely because one recent delivery was fast.
Practical questions
Is the promised lead time the observed lead time? No. A promise describes a commitment or expectation; the observed duration depends on recorded start and end events. Keep both so the difference can be investigated.
How should partial deliveries be handled? Record each receipt and its quantity, then calculate against the agreed end event. Mixing first receipt for some orders with complete receipt for others creates an inconsistent comparison.
Does a missing receipt record prove supplier failure? No. Check the source evidence and data-entry process. Record the uncertainty rather than assigning a cause before it is established.
How does this differ from OTIF? The log describes elapsed time between events. HPA’s supplier delivery scorecard guide addresses whether deliveries meet agreed time and quantity conditions. The measures answer related but different questions.
Connect the log to a learning requirement
For a wider view of event coverage and data ownership, read the supply chain visibility guide. If your role involves planning and inventory, compare the published CPIM preparation course outline with your learning needs; confirm with HPA which topics and practical applications are included.
For a team discussion, use HPA corporate training and describe the roles, planning decision, current data gaps, group size and preferred delivery arrangements. Share anonymised sample records rather than confidential supplier terms. A specific brief helps the team assess course fit without promising an operational result.